BIM is changing how buildings, infrastructure, and utilities are planned, designed, built and managed. The accuracy of the BIM model is dependent on an accurate asbuilt at the beginning of the project. Survey Systems is on the leading edge of new technology in developing high-definition scanning for accurate, comprehensive, 3D models, the foundation of BIM.

HDS project application

  • Asbuilt Surveys
  • Infrastructure Compliance Surveys
  • Construction Compliance Surveys
  • Historical Documentation
  • Architectural Modeling
  • Forensics Surveys

HDS PROJECT APPLICATION

  • Asbuilt Surveys
  • Infrastructure Compliance Surveys
  • Construction Compliance Surveys
  • Historical Documentation
  • Architectural Modeling
  • Forensics Surveys

HDS Deliverables

  • Land Surveys
  • Point Clouds
  • 2D & 3D CAD
  • BIM Models (Any Format)
  • Animation and Model Fly Throughs
  • Leica TruViews ™
  • Navisworks ™

ALTA/ACSM

  • Gilcrest Reservoir, Platteville, CO, The Bromley Companies
    SSI performed a full ALTA/ACSM land title survey on 1200 acre property.
  • Alexan at Briargate, Colorado Springs, CO, Trammel Crow Residential.
    SSI performed a full ALTA/ACSM land title survey. Post-construction survey and update.
  • Alexan at Littleton, Denver, CO, Trammel Crow Residential
    SSI performed a full ALTA/ACSM land title survey, post-contruction survey and update.

Construction

  • Peakview 360 Apartments, Centennial, CO, Forestar (USA) Real Estate Group, Inc.
    SSI provided survey support and construction layout.
  • Alexan at Prospect, Denver, CO, Trammel Crow Residential
    PROJECT DETAILS
  • Alexan at Briargate, Colorado Springs, CO, Trammel Crow Residential
  • Alexan at Littleton, Littleton, Colorado, Trammel Crow Residential
  • Denver Union Station, Denver, CO, Milender White Construction Company.
    SSI provided full survey support.
  • DHA Mariposa, Denver, CO, Milender White Construction Company
    SSI provided full survey support.

Engineering Support

  • BNSF Storm Water Drainage Improvements, Denver, CO, AECOM
    PROJECT DETAILS
  • Various Engineering Projects, Denver Metro Area, Deere & Ault Consultants

Federal Contracting

  • Buckley Air Force Base, Buckley AFB, Aurora, CO, MCS CC&D, LLC
  • United States Air Force Academy Water Line Improvements,
    Colorado Springs, CO, CDM
    PROJECT DETAILS
  • Colorado Department of Military Veterans Affairs – Readiness Center,
    Ft. Lupton, CO, GH Phipps

Heavy Civil

  • VA Replacement Medical Center, Aurora, CO, Kiewit-Turner Joint Venture
    SSI provided full survey support and survey consultant for KTVA. SSI is also providing survey support for various other sub-contractors working on site.
    PROJECT DETAILS

Hydrographic Survey

  • Volumetric Survey for Existing Reservoirs, Deere & Ault Consultants, City of Aurora, United Water and Sanitation District, Ecological Resources
    SSI provided services in determining sediment loading in reservoirs.

Mining Support

  • Intrepid Potash Mine Site, Insitu-Mining Project, Carlsbad, NM
    SSI provided full surveying support below and above ground.
    PROJECT DETAILS

Oil and Gas

  • Stapleton Re-Alignment, Denver, CO, ConocoPhillips
  • Water Rights
  • Dry-up and legal descriptions, Weld County, CO, United Water, LLC
PROJECT DETAILS

VA Replacement Medical Center Facility

Eastern Colorado Health Care System

Client

Department of Veterans Affairs, Kiewit-Turner Joint Venture
, Fiore & Sons, Centerre Construction, Holland Construction,
Weifield Construction, Berg Electric Corp., T.B. Penick & Sons, Inc.

Project Location

Fitzsimmons Campus, Aurora, CO

Project Description

The new 182-bed medical center will include inpatient tertiary care and ambulatory care, a 30-bed Spinal Cord Injury/Disorder Center, a 30-bed nursing home community living center, a research building, and parking structures.
Project Scope includes a 1.1m Square-Foot Building, 31-Acre Site, Two Inpatient Buildings, Two Clinic Buildings, Diagnostic and Treatment Center, Research Building, Community Living Center, Concourse, Energy Center, Staff and Visitor Parking (2,000 Stalls), 500,000 Cubic Yards Excavation, 130,000 Cubic Yards Backfill, Seeking LEED Silver certification

Survey Scope

Full-service land surveying support for a new veterans administration hospital and medical center at the Fitzsimons Campus in Aurora, Colorado. SSI is providing two full-time crews and a professional land surveyor plus office support and equipment to construct nine buildings, three parking garages and one concourse on a 31-acre site.

Performance Period

April 2011 – February 2016

Return to top of page

 

Alexan at Prospect

Client

Trammell Crow Residential

Project Location

Denver, CO

Project Description

A six-story multi-phase structure that was comprised of seven connected buildings built as separate structures. The project was complicated due to the following issues:

  • It was a confined small site that was bordered on the west and north by a major BNSF rail spur and on the south by a toll-way flyover and to the east by an existing 6-story structure.
  • The central structure was a precast parking structure.
  • There were critical connections to the parking structure and as each phase connected to each other.

SSI exceeded all expectations and completed what was thought of as being un-buildable while ensuring all seven buildings connected at precise locations and completed the project ahead of schedule by 6-months. We identified numerous areas of potential interference and worked with the design consultants to ensure the project proceeded on schedule and reduced the delays that would have been eminent.

The project required 1st order control surveying for the pre-cast parking structure (foundations and podium deck control on seven connected buildings surrounding a precast parking structure).

At the time, this site was the largest drilled pier project in the State of Colorado and while under construction was the largest drilled pier project under construction in the United States.

Survey Scope

First Order Control Surveying For Pre-Cast Structure, Full Survey Support, Largest Drill Pier Project In Colorado, Consultation

Performance Period

December 2008 – June 2010

Return to top of page

 

Intrepid Postash Mine Site

Client

Intrepid Potash LLC c/o AMEC Americas Ltd.

Project Location

Carlsbad, New Mexico

Project Description & Survey Scope

HB, New Cap Rock Water Line, LRIP, North Mine Compaction Plant, West Mine Mill Site and Brine Plant

HB Solution Mining Project

Injection and Extraction Site Locations for Well Installation

SSI coordinated with Intrepid staff and consultants to determine the locations for injection and extraction wells for the project.

Injection and Extraction Piping Alignments


SSI Coordinated with Intrepid staff and consultants to determine the most advantageous route for the injection and extraction piping to serve the project. SSI supplied all shape files and legal descriptions for submittals to the BLM on the project.

Solar Pond and Mill Site Support

SSI delivered all legal descriptions and support to re-locate existing utilities in the proposed solar ponds and mill site areas.

New Cap Rock Water Line


SSI located and acquired a new water line to serve the Intrepid companies. Total alignment acquired in excess of 40 miles. Coordinated with Private as well as public land owners to determine the most advantageous route to acquire a pipeline easement.

Construction Support for all Projects


SSI provided our services to assist Intrepid in the following projects

  • LRIP Intrepid East Mine
  • North Mine New Compactor Plant
  • West Mine New Mill Site and Brine Plant
  • Alignment staking for 38 Miles for the HB Project

Performance Period

June 2008 – Current

Return to top of page

 

United States Air Force Academy Water Line Improvements

Client

CDM

Project Location

Colorado Springs, Colorado

Project Description

Project included three separate areas of water line improvements that when completed consisted of over 30,000 L.F. of HDPE fused pipe. SSI was responsible for control throughout the entire project.

Performance Period

February 2010 – June 2010

Return to top of page

 

BNSF Storm Water Drainage Improvements, Denver, Colorado

Client

AECOM

Project Location

Denver, Colorado

Project Description

Project included setting site control on the Denver intermodal terminal that was in excess of 6,000 feet in length and included two spur lines with an aging centrally located storm water collection structure. SSI as-built the entire storm water structure and collected site topography for the client to design a new storm water and oil interceptor system for the entire alignment.

Performance Period

July 2010

Return to top of page